πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

ONSHORE WIND Β· SPP

Onshore wind project GEN-2018-014, Holt County

Onshore wind project GEN-2018-014, Holt County is a 74.1 MW onshore wind request withdrawn in the SPP interconnection queue, in Holt County, Missouri, connecting to TMO.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2018 (completed)
  2. Withdrawn / abandonedApr 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2024 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2018-014
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
TMO
Connection point (POI)
Holt County 345kV Substation
Location
Holt County, Missouri
Technology
Wind: 74.1 MW
Total requested
74.1 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
27 April 2018
Proposed online date
December 2024
Came online
December 2024
Withdrawn
April 2023

Location

Marker shows the centre of Holt County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Holt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem