πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

OTHER Β· NYISO

AES Smithtown Gen

AES Smithtown Gen is a 510 MW other request withdrawn in the NYISO interconnection queue, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2000 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
50
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
AES Long Island, LLC
Connection point (POI)
LIPA System
Location
New York
Technology
Other: 510 MW
Total requested
510 MW
Queue status
Withdrawn
Entered queue
10 February 2000

Location

No county location in the queue data.

Power plants in New York Β· Transmission lines in New York

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem