πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

ONSHORE WIND Β· WEST

Onshore wind project 98, Benton County

Onshore wind project 98, Benton County is a 150 MW onshore wind request withdrawn in the West interconnection queue, in Benton County, Washington, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2006 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
98
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Gaelectric
Connection point (POI)
TBD
Location
Benton County, Washington
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
17 October 2006
Proposed online date
September 2008

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem