ONSHORE WIND Β· ERCOT

Cameron County Wind

Cameron County Wind is a 165 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Mar 2009 (completed)
  2. ConsentedAug 2013 (completed)
  3. Construction (completed)
  4. OperatingJan 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
11INR0057
Grid region
ERCOT (Texas)
Developer
Apex Clean
Connection point (POI)
approx bus 5761
Technology
Wind: 165 MW
Total requested
165 MW
Study phase
IA
Queue status
Operational
Entered queue
2 March 2009
Agreement signed
9 August 2013
Proposed online date
January 2016
Came online
January 2016

Location

No county location in the queue data.