ONSHORE WIND Β· ERCOTTrinity Hills
Trinity Hills is a 225 MW onshore wind request built and operating in the ERCOT interconnection queue.
Request details
- Queue ID
- 08INR0062
- Grid region
- ERCOT (Texas)
- Developer
- BP Wind Energy North America, Inc
- Connection point (POI)
- TRI_TH1_BUS134.500
- Technology
- Wind: 225 MW
- Total requested
- 225 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 25 June 2007
- Agreement signed
- 1 October 2010
- Proposed online date
- December 2011