United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· ERCOT

Shawnee Bottom Solar

Shawnee Bottom Solar is a 153 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
26INR0281
Grid region
ERCOT (Texas)
Developer
Shawnee Bottom Solar, LLC
Connection point (POI)
tap 138kV 3319 REDLAND_8 - 3120 NACOGDSE_8
Technology
Solar: 153 MW
Total requested
153 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
22 September 2023
Proposed online date
June 2026

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem