ONSHORE WIND · MISO

Onshore wind project G503, Huron County

Onshore wind project G503, Huron County is a 158 MW onshore wind request built and operating in the MISO interconnection queue, in Huron County, Michigan.

Queue statusOperating
  1. PlanningQueued Mar 2005 (completed)
  2. ConsentedJan 2008 (completed)
  3. Construction (completed)
  4. OperatingOct 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G503
Grid region
MISO (Midcontinent)
Connection point (POI)
Sanduskey - Wyatt 120 kV
Location
Huron County, Michigan
Technology
Wind: 158 MW
Total requested
158 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
14 March 2005
Agreement signed
8 January 2008
Proposed online date
October 2008
Came online
October 2008

Location

Marker shows the centre of Huron County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan