GAS Β· ERCOTIndeck Wharton
Indeck Wharton is a 654 MW gas request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2012 (completed)
- Withdrawn / abandonedSep 2018 (project stopped here)
- ConsentedSep 2014 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 15INR0023
- Grid region
- ERCOT (Texas)
- Developer
- Indeck
- Connection point (POI)
- tap 345kV 44200 Hillje - 44000 WAP
- Technology
- Gas: 654 MW
- Total requested
- 654 MW
- Study phase
- IA
- Queue status
- Withdrawn
- Entered queue
- 5 November 2012
- Agreement signed
- 15 September 2014
- Proposed online date
- September 2021
- Withdrawn
- September 2018
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem