United States › Grid › Interconnection queues › New York

SOLAR + STORAGE · NYISO

Harvest Hills Solar 2

Harvest Hills Solar 2 is a 100 MW solar + storage request withdrawn in the NYISO interconnection queue, in Cayuga County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1238
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
ConnectGen Cayuga County LLC
Connection point (POI)
Wright Avenue - Milliken 115kV line
Location
Cayuga County, New York
Technology
Solar: 100 MW · Battery
Total requested
100 MW
Queue status
Withdrawn
Entered queue
25 August 2021

Location

Marker shows the centre of Cayuga County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Cayuga County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem