United States βΊ Grid βΊ Interconnection queues βΊ South Carolina
BATTERY STORAGE Β· SOUTHEASTBattery storage project 252, Florence County
Battery storage project 252, Florence County is a 75.0 MW battery storage request withdrawn in the Southeast interconnection queue, in Florence County, South Carolina, connecting to Santee Cooper.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 252
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Santee Cooper
- Location
- Florence County, South Carolina
- Technology
- Battery: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 1 February 2024
- Proposed online date
- December 2028
Location
Marker shows the centre of Florence County; the queue data does not give exact sites.
Power plants in South Carolina Β· Transmission lines in South Carolina
Other requests in Florence County
- Solar project 915787, Florence CountySolar Β· 65.0 MW Β· in study
- Solar project 977864, Florence CountySolar Β· 5.0 MW Β· in study
- Solar project 977879, Florence CountySolar Β· 5.0 MW Β· in study
- Solar project 957087, Florence CountySolar Β· 5.0 MW Β· in study
- Solar project 956532, Florence CountySolar Β· 4.5 MW Β· in study
- Other project 8615, Florence CountyOther Β· 10.0 MW Β· built
- Coal project 25, Florence CountyCoal Β· 609 MW Β· withdrawn
- Coal project 26, Florence CountyCoal Β· 609 MW Β· withdrawn
- Gas project 315, Florence CountyGas Β· 149 MW Β· withdrawn
- Solar project 22136, Florence CountySolar Β· 75.5 MW Β· withdrawn
- Solar project 243, Florence CountySolar Β· 75.0 MW Β· withdrawn
- Solar project 19397, Florence CountySolar Β· 75.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem