HYDRO Β· WEST

Hydro project 59

Hydro project 59 is a 2.2 MW hydro request withdrawn in the West interconnection queue, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
59
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Need more information
Technology
Hydro: 2.2 MW
Total requested
2.2 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
17 April 2007
Proposed online date
October 2007

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem