United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Cottonwood Wind

Cottonwood Wind is a 100 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2005 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedNov 2006 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
04INR0011c
Grid region
ERCOT (Texas)
Developer
Texas Land Partners
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
IA
Queue status
Withdrawn
Entered queue
19 October 2005
Agreement signed
29 November 2006
Proposed online date
December 2050

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem