Solar + storage project G0661, Benton County

Solar + storage project G0661, Benton County is a 450 MW solar + storage request withdrawn in the West interconnection queue, in Benton County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0661
Grid region
West (non-ISO utilities)
Connection point (POI)
Bofer Canyon Substation
Location
Benton County, Washington
Technology
Solar: 300 MW Β· Battery: 150 MW
Total requested
450 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
16 December 2020
Proposed online date
October 2023

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Benton County