SOLAR Β· PJM

Solar project AI2-026, Buckingham County

Solar project AI2-026, Buckingham County is a 100 MW solar request withdrawn in the PJM interconnection queue, in Buckingham County, Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2022 (completed)
  2. Withdrawn / abandonedSep 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AI2-026
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Buckingham-Bremo 230 kV
Location
Buckingham County, Virginia
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
22 December 2022
Proposed online date
December 2028
Withdrawn
September 2024

Location

Marker shows the centre of Buckingham County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Buckingham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem