πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

SOLAR Β· PJM

Solar project AF1-116, Washington County

Solar project AF1-116, Washington County is a 120 MW solar request withdrawn in the PJM interconnection queue, in Washington County, Kentucky, connecting to EKPC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2019 (completed)
  2. Withdrawn / abandonedFeb 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF1-116
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
EKPC
Developer
Logan Branch Solar, LLC
Connection point (POI)
Marion County 161 kV
Location
Washington County, Kentucky
Technology
Solar: 120 MW
Total requested
120 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Withdrawn
Entered queue
12 September 2019
Proposed online date
December 2023
Withdrawn
February 2025

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Washington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem