πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

ONSHORE WIND Β· MISO

Onshore wind project H086, Monroe County

Onshore wind project H086, Monroe County is a 299 MW onshore wind request withdrawn in the MISO interconnection queue, in Monroe County, Missouri.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2008 (completed)
  2. Withdrawn / abandonedJul 2012 (project stopped here)
  3. ConsentedJul 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H086
Grid region
MISO (Midcontinent)
Connection point (POI)
10 miles N of Spencer Creek sub
Location
Monroe County, Missouri
Technology
Wind: 299 MW
Total requested
299 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
9 July 2008
Agreement signed
2 July 2012
Proposed online date
December 2012
Withdrawn
July 2012

Location

Marker shows the centre of Monroe County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem