United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project J3661, Henry County
Onshore wind project J3661, Henry County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Henry County, Iowa, connecting to AMEREN MISSOURI.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedSep 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3661
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN MISSOURI
- Connection point (POI)
- 7MAYWOOD - 7SUB T 3 345.0kV
- Location
- Henry County, Iowa
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 14 April 2024
- Proposed online date
- September 2028
- Withdrawn
- September 2025
Location
Marker shows the centre of Henry County; the queue data does not give exact sites.
Other requests in Henry County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem