United States βΊ Grid βΊ Interconnection queues
ONSHORE WIND Β· ERCOTWIT Ranch Wind
WIT Ranch Wind is a 161 MW onshore wind request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2017 (completed)
- Withdrawn / abandonedNov 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 19INR0108
- Grid region
- ERCOT (Texas)
- Developer
- Eon
- Connection point (POI)
- 6050 Lake Pauline 138kV
- Technology
- Wind: 161 MW
- Total requested
- 161 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 9 August 2017
- Proposed online date
- December 2019
- Withdrawn
- November 2018
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem