United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Scandia Wind F

Scandia Wind F is a 200 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2009 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedApr 2014 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
13INR0010f
Grid region
ERCOT (Texas)
Developer
Scandia Southwest
Connection point (POI)
Windmill (79502)
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
IA and FIS Pending
Queue status
Withdrawn
Entered queue
29 June 2009
Agreement signed
25 April 2014
Proposed online date
July 2017

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem