BATTERY STORAGE Β· SOUTHEASTBattery storage project 269, Orangeburg County
Battery storage project 269, Orangeburg County is a 150 MW battery storage request withdrawn in the Southeast interconnection queue, in Orangeburg County, South Carolina, connecting to Santee Cooper.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 269
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Santee Cooper
- Location
- Orangeburg County, South Carolina
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 5 June 2024
- Proposed online date
- June 2028
Location
Marker shows the centre of Orangeburg County; the queue data does not give exact sites.
Power plants in South Carolina Β· Transmission lines in South Carolina
Other requests in Orangeburg County
- Solar + storage project 137, Orangeburg CountySolar + storage Β· 100 MW Β· under construction
- Solar project 39, Orangeburg CountySolar Β· 42.0 MW Β· under construction
- Solar + storage project 20210310001, Orangeburg CountySolar + storage Β· 100 MW Β· in study
- Solar project 272, Orangeburg CountySolar Β· 74.9 MW Β· in study
- Solar + storage project 20230829012, Orangeburg CountySolar + storage Β· 74.9 MW Β· in study
- Solar project 286, Orangeburg CountySolar Β· 60.0 MW Β· in study
- Solar project 20240829003, Orangeburg CountySolar Β· 300 MW Β· withdrawn
- Solar + storage project 233, Orangeburg CountySolar + storage Β· 120 MW Β· withdrawn
- Solar project 20151028001, Orangeburg CountySolar Β· 113 MW Β· withdrawn
- Solar project 97, Orangeburg CountySolar Β· 100 MW Β· withdrawn
- Solar project 20171018010, Orangeburg CountySolar Β· 100 MW Β· withdrawn
- Solar project 113, Orangeburg CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem