Solar project 25-IC-AF

Solar project 25-IC-AF is a 74.9 MW solar request withdrawn in the Southeast interconnection queue, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedApr 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25-IC-AF
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Clay - Rainbow City SS 115 kV Line
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Withdrawn
April 2025

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem