United States βΊ Grid βΊ Interconnection queues βΊ South Carolina
SOLAR Β· SOUTHEASTSolar project 76, Charleston County
Solar project 76, Charleston County is a 100 MW solar request withdrawn in the Southeast interconnection queue, in Charleston County, South Carolina, connecting to Santee Cooper.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2018 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 76
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Santee Cooper
- Location
- Charleston County, South Carolina
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 4 January 2018
- Proposed online date
- December 2019
Location
Marker shows the centre of Charleston County; the queue data does not give exact sites.
Power plants in South Carolina Β· Transmission lines in South Carolina
Other requests in Charleston County
- Solar project 20181030001, Charleston CountySolar Β· 160 MW Β· in study
- Solar project 20181030002, Charleston CountySolar Β· 103 MW Β· in study
- Solar project 20171113002, Charleston CountySolar Β· 102 MW Β· withdrawn
- Solar project 20171215001, Charleston CountySolar Β· 87.5 MW Β· withdrawn
- Battery storage project 20191204001, Charleston CountyBattery storage Β· 10.0 MW Β· withdrawn
- Battery storage project 20200720003, Charleston CountyBattery storage Β· 2.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem