United States βΊ Grid βΊ Interconnection queues
SOLAR Β· ERCOTLunis Creek Solar 3
Lunis Creek Solar 3 is a 212 MW solar request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 21INR0547
- Grid region
- ERCOT (Texas)
- Developer
- Lunis Creek Solar Project, LLC
- Connection point (POI)
- tap the 345 kV Whitepoint (#8956) - South Texas Project (#5915); AEP
- Technology
- Solar: 212 MW
- Total requested
- 212 MW
- Study phase
- FIS & SS Incomplete
- Queue status
- Withdrawn
- Proposed online date
- December 2023
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem