United States βΊ Grid βΊ Interconnection queues
ONSHORE WIND Β· ERCOTEaster Wind B
Easter Wind B is a 153 MW onshore wind request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2013 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 15INR0063b
- Grid region
- ERCOT (Texas)
- Developer
- TriGlobal
- Connection point (POI)
- tap 345kV 79501 Ogallala - 79502 Windmill
- Technology
- Wind: 153 MW
- Total requested
- 153 MW
- Study phase
- FIS Complete
- Queue status
- Withdrawn
- Entered queue
- 18 December 2013
- Proposed online date
- October 2020
Location
No county location in the queue data.