United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Easter Wind B

Easter Wind B is a 153 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
15INR0063b
Grid region
ERCOT (Texas)
Developer
TriGlobal
Connection point (POI)
tap 345kV 79501 Ogallala - 79502 Windmill
Technology
Wind: 153 MW
Total requested
153 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
18 December 2013
Proposed online date
October 2020

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem