SOLAR Β· ERCOT

Barilla Solar 2

Barilla Solar 2 is a 21.0 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2010 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedDec 2013 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
12INR0059c
Grid region
ERCOT (Texas)
Developer
First Solar
Connection point (POI)
181651 Hovey 34.5kV
Technology
Solar: 21.0 MW
Total requested
21.0 MW
Study phase
IA and FIS Pending
Queue status
Withdrawn
Entered queue
1 December 2010
Agreement signed
26 December 2013
Proposed online date
December 2017

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem