United States βΊ Grid βΊ Interconnection queues
SOLAR Β· ERCOTBarilla Solar 2
Barilla Solar 2 is a 21.0 MW solar request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2010 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedDec 2013 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 12INR0059c
- Grid region
- ERCOT (Texas)
- Developer
- First Solar
- Connection point (POI)
- 181651 Hovey 34.5kV
- Technology
- Solar: 21.0 MW
- Total requested
- 21.0 MW
- Study phase
- IA and FIS Pending
- Queue status
- Withdrawn
- Entered queue
- 1 December 2010
- Agreement signed
- 26 December 2013
- Proposed online date
- December 2017
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem