GAS Β· ERCOTDeer Park Energy Center
Deer Park Energy Center is a 190 MW gas request built and operating in the ERCOT interconnection queue.
Request details
- Queue ID
- 14INR0015
- Grid region
- ERCOT (Texas)
- Developer
- Calpine
- Technology
- Gas: 190 MW
- Total requested
- 190 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 28 July 2011
- Agreement signed
- 2 January 2013
- Proposed online date
- July 2014
- Came online
- July 2014