ONSHORE WIND Β· WEST

Onshore wind project G0430, Benton County

Onshore wind project G0430, Benton County is a 200 MW onshore wind request withdrawn in the West interconnection queue, in Benton County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2010 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0430
Grid region
West (non-ISO utilities)
Connection point (POI)
Red Mountain Sub
Location
Benton County, Washington
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
14 May 2010
Proposed online date
December 2013

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem