πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

SOLAR Β· MISO

Solar project J3263, Desha County

Solar project J3263, Desha County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Desha County, Arkansas, connecting to ARKANSAS ELECTRIC COOPERATIVE CORPORATION.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedSep 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3263
Grid region
MISO (Midcontinent)
Utility / transmission owner
ARKANSAS ELECTRIC COOPERATIVE CORPORATION
Connection point (POI)
DUMAS - REED SS 115.0kV
Location
Desha County, Arkansas
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
15 April 2024
Proposed online date
June 2028
Withdrawn
September 2025

Location

Marker shows the centre of Desha County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Desha County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem