πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

GAS Β· ERCOT

Wharton County Generation #2

Wharton County Generation #2 is a 660 MW gas request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
12INR0020
Grid region
ERCOT (Texas)
Developer
Suez Energy, NA
Technology
Gas: 660 MW
Total requested
660 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
28 October 2008
Proposed online date
December 2050

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem