United States βΊ Grid βΊ Interconnection queues
BATTERY STORAGE Β· SPPBattery storage project GEN-2022-146
Battery storage project GEN-2022-146 is a 150 MW battery storage request withdrawn in the SPP interconnection queue, connecting to EDE.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2023 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-146
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- EDE
- Connection point (POI)
- Asbury 161 kV Substation
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 24 February 2023
- Proposed online date
- December 2027
- Withdrawn
- November 2023
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem