ONSHORE WIND Β· ERCOT

Bull Creek Wind Plant

Bull Creek Wind Plant is a 180 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Mar 2006 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget May 2009 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
07INR0037
Grid region
ERCOT (Texas)
Developer
BNB Renewable Energy, LLC
Connection point (POI)
BULLCRK_WND134.500
Technology
Wind: 180 MW
Total requested
180 MW
Study phase
FIS Complete
Queue status
Operational
Entered queue
17 March 2006
Proposed online date
May 2009

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem