ONSHORE WIND Β· ERCOT

Windthorst-2 Wind Farm

Windthorst-2 Wind Farm is a 94.0 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2009 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
11INR0076
Grid region
ERCOT (Texas)
Developer
Windthorst-2, LLC
Technology
Wind: 94.0 MW
Total requested
94.0 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
15 October 2009
Proposed online date
December 2050

Location

No county location in the queue data.

Power plants in Β· Transmission lines in