United States βΊ Grid βΊ Interconnection queues βΊ New York
GAS Β· NYISORiver Hill Project
River Hill Project is a 290 MW gas request withdrawn in the NYISO interconnection queue, in Chemung County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2002 (completed)
- Withdrawn / abandonedJul 2008 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 111
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- River Hill Power Co., LLC
- Connection point (POI)
- Homer City-Watercure 345kV
- Location
- Chemung County, New York
- Technology
- Gas: 290 MW
- Total requested
- 290 MW
- Queue status
- Withdrawn
- Entered queue
- 5 February 2002
- Withdrawn
- July 2008
Location
Marker shows the centre of Chemung County; the queue data does not give exact sites.
Other requests in Chemung County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem