United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· ERCOT

GSE Three Solar

GSE Three Solar is a 50.0 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
19INR0094
Grid region
ERCOT (Texas)
Developer
Alpin Sun
Connection point (POI)
6044 Turkey 69kV
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
23 June 2017
Proposed online date
April 2019

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem