United States βΊ Grid βΊ Interconnection queues βΊ New York
OTHER Β· NYISONeptune DC PJM-NYC
Neptune DC PJM-NYC is a 600 MW other request withdrawn in the NYISO interconnection queue, connecting to CONED.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2001 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 0089A
- Grid region
- NYISO (New York)
- Utility / transmission owner
- CONED
- Developer
- Atlantic Energy, LLC
- Connection point (POI)
- W49th St
- Location
- New York
- Technology
- Other: 600 MW
- Total requested
- 600 MW
- Queue status
- Withdrawn
- Entered queue
- 15 March 2001
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem