🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Kentucky

GAS · MISO

Gas project G019, Oldham County

Gas project G019, Oldham County is a 750 MW gas request built and operating in the MISO interconnection queue, in Oldham County, Kentucky.

Queue statusOperating
  1. PlanningQueued Dec 1999 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2004 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G019
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Oldham County, Kentucky
Technology
Gas: 750 MW
Total requested
750 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
7 December 1999
Proposed online date
June 2004
Came online
June 2004

Location

Marker shows the centre of Oldham County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Oldham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem