United States βΊ Grid βΊ Interconnection queues
ONSHORE WIND Β· ERCOTPampa Wind
Pampa Wind is a 500 MW onshore wind request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2008 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedNov 2013 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 12INR0018
- Grid region
- ERCOT (Texas)
- Developer
- Avangrid
- Connection point (POI)
- 79000 Gray 345kV
- Technology
- Wind: 500 MW
- Total requested
- 500 MW
- Study phase
- IA and FIS Pending
- Queue status
- Withdrawn
- Entered queue
- 15 September 2008
- Agreement signed
- 12 November 2013
- Proposed online date
- December 2019
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem