OTHER Β· PJMAC Landfill Energy Units 1, 2, 3
AC Landfill Energy Units 1, 2, 3 is a 100 MW other request withdrawn in the PJM interconnection queue, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2007 (completed)
- Withdrawn / abandonedFeb 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- S07
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Keystone-Branchburg
- Technology
- Other: 100 MW
- Total requested
- 100 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: System Impact Study, Facilities Study
- Queue status
- Withdrawn
- Entered queue
- 1 March 2007
- Withdrawn
- February 2013
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem