ONSHORE WIND Β· ERCOT

Horse Hollow 3

Horse Hollow 3 is a 224 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Jul 2005 (completed)
  2. ConsentedMar 2006 (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2009 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
06INR0040
Grid region
ERCOT (Texas)
Developer
FPL Energy Horse Hollow Wind LP
Connection point (POI)
HHG_HHOLLOW334.500
Technology
Wind: 224 MW
Total requested
224 MW
Study phase
IA
Queue status
Operational
Entered queue
29 July 2005
Agreement signed
24 March 2006
Proposed online date
October 2009

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem