πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

BATTERY STORAGE Β· WEST

Battery storage project 2022-G14

Battery storage project 2022-G14 is a 200 MW battery storage request withdrawn in the West interconnection queue, connecting to WAPA Rocky Mountain Region.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2022-G14
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Rocky Mountain Region
Connection point (POI)
Rifle Substation -
Technology
Battery: 200 MW
Total requested
200 MW
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
14 December 2022
Proposed online date
December 2025

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem