United States βΊ Grid βΊ Interconnection queues βΊ Missouri
SOLAR Β· SPPSolar project GEN-2016-168, Lafayette County
Solar project GEN-2016-168, Lafayette County is a 20.0 MW solar request withdrawn in the SPP interconnection queue, in Lafayette County, Missouri, connecting to KCPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2016 (completed)
- Withdrawn / abandonedJul 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2016-168
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- KCPL
- Connection point (POI)
- Higginsville 69 kV Sub
- Location
- Lafayette County, Missouri
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 30 November 2016
- Proposed online date
- September 2019
- Withdrawn
- July 2018
Location
Marker shows the centre of Lafayette County; the queue data does not give exact sites.
Other requests in Lafayette County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem