πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

SOLAR Β· SPP

Solar project GEN-2016-168, Lafayette County

Solar project GEN-2016-168, Lafayette County is a 20.0 MW solar request withdrawn in the SPP interconnection queue, in Lafayette County, Missouri, connecting to KCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedJul 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2016-168
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
KCPL
Connection point (POI)
Higginsville 69 kV Sub
Location
Lafayette County, Missouri
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 November 2016
Proposed online date
September 2019
Withdrawn
July 2018

Location

Marker shows the centre of Lafayette County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Lafayette County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem