SOLAR Β· ERCOT

RE Roserock Solar

RE Roserock Solar is a 160 MW solar request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Apr 2014 (completed)
  2. ConsentedNov 2015 (completed)
  3. Construction (completed)
  4. OperatingNov 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
16INR0048
Grid region
ERCOT (Texas)
Developer
Recurrent Energy
Connection point (POI)
approx bus 60384 Clovis 138kV
Technology
Solar: 160 MW
Total requested
160 MW
Study phase
IA
Queue status
Operational
Entered queue
9 April 2014
Agreement signed
19 November 2015
Proposed online date
October 2016
Came online
November 2016

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem