πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Hampshire

OTHER Β· ISO-NE

Landfill Gas

Landfill Gas is a 0.8 MW other request withdrawn in the ISO-NE interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandonedJul 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
264
Grid region
ISO-NE (New England)
Connection point (POI)
NHEC 12.5 kV circuit
Location
New Hampshire
Technology
Other: 0.8 MW
Total requested
0.8 MW
Service type
Other
Queue status
Withdrawn
Entered queue
4 June 2008
Proposed online date
November 2008
Withdrawn
July 2008

Location

No county location in the queue data.

Power plants in New Hampshire Β· Transmission lines in New Hampshire

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem