United States βΊ Grid βΊ Interconnection queues βΊ District of Columbia
GAS Β· PJMGas project W3-155
Gas project W3-155 is a 20.0 MW gas request withdrawn in the PJM interconnection queue, connecting to PEPCO.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2010 (completed)
- Withdrawn / abandonedAug 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- W3-155
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PEPCO
- Connection point (POI)
- Alabama 13.8kV
- Location
- District of Columbia
- Technology
- Gas: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 29 October 2010
- Proposed online date
- February 2014
- Withdrawn
- August 2013
Location
No county location in the queue data.
Power plants in District of Columbia Β· Transmission lines in District of Columbia
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem