BATTERY STORAGE Β· ERCOT

Jerboa BESS

Jerboa BESS is a 201 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
27INR0068
Grid region
ERCOT (Texas)
Developer
Jerboa Storage, LLC
Connection point (POI)
Tap 138kV 8906 North Alamo - 8354 Weslaco Switching Station
Technology
Battery: 201 MW
Total requested
201 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
14 August 2023
Proposed online date
February 2027

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem