ONSHORE WIND Β· ERCOT

Cedro Hill Wind

Cedro Hill Wind is a 150 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Jan 2009 (completed)
  2. ConsentedSep 2009 (completed)
  3. Construction (completed)
  4. OperatingTarget Nov 2010 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
09INR0082
Grid region
ERCOT (Texas)
Developer
DKRW Wind, LLC
Connection point (POI)
CEDROHI_CHW134.500
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
IA
Queue status
Operational
Entered queue
9 January 2009
Agreement signed
14 September 2009
Proposed online date
November 2010

Location

No county location in the queue data.

Power plants in Β· Transmission lines in