United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
OTHER Β· MISOOther project J117, Brown County
Other project J117, Brown County is a 9.1 MW other request withdrawn in the MISO interconnection queue, in Brown County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2010 (completed)
- Withdrawn / abandonedSep 2010 (project stopped here)
- ConsentedSep 2010 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J117
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- substation at 625 E Lincoln Street, Springfield, MN
- Location
- Brown County, Minnesota
- Technology
- Diesel: 9.1 MW
- Total requested
- 9.1 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 16 February 2010
- Agreement signed
- 20 September 2010
- Proposed online date
- June 2016
- Withdrawn
- September 2010
Location
Marker shows the centre of Brown County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Brown County