United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

BATTERY STORAGE Β· SOUTHEAST

Battery storage project LGE-GIS-2021-014, Bullitt County

Battery storage project LGE-GIS-2021-014, Bullitt County is a 300 MW battery storage request withdrawn in the Southeast interconnection queue, in Bullitt County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedSep 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
LGE-GIS-2021-014
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Louisville Gas & Electric and Kentucky Utilities Energy
Connection point (POI)
Blue Lick 345 kV
Location
Bullitt County, Kentucky
Technology
Battery: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
30 March 2021
Proposed online date
December 2025
Withdrawn
September 2023

Location

Marker shows the centre of Bullitt County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Bullitt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem