ONSHORE WIND Β· ERCOT

Trans Pecos Windfarm

Trans Pecos Windfarm is a 200 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
10INR0049
Grid region
ERCOT (Texas)
Developer
RES America Developments
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
6 June 2008

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem