πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

GAS Β· PJM

Kearny #12

Kearny #12 is a 7.0 MW gas request built and operating in the PJM interconnection queue, in Hudson County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Mar 2001 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2001 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G08
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Kearny
Location
Hudson County, New Jersey
Technology
Gas: 7.0 MW
Total requested
7.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
13 March 2001
Proposed online date
June 2001
Came online
June 2001

Location

Marker shows the centre of Hudson County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Hudson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem